Practicing Success

Target Exam

CUET

Subject

General Test

Chapter

Numerical Ability

Topic

Time and Work

Question:

A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, $\frac{3}{5}$ of the work is completed. How many additional men may be employed, so that the work may be completed in time, each man now working 17 hours per day?

Options:

532

495

528

514

Correct Answer:

528

Explanation:

Formula to be used here, 

\(\frac{M_1\;×\;D_1\;×\;H_1}{M_2\;×\;D_2\;×\;H_2}\)=\(\frac{W_1}{W_2}\)

where, M = No. of men, D = No. of days, H = No. of hours, W = Work

⇒ Putting values, 

⇒ \(\frac{187\;×\;65\;×\;15}{M_2\;×\;10\;×\;17}\) = \(\frac{3/5}{2/5}\)

⇒ \( { M}_{2 } \) = 715,

⇒ Extra Men needed = 715 - 187 = 528 men.