Which of the following statements about the plans of Mitticool are correct?
A. The policy of keeping all products at a lower rate is a standing plan.
B. Starting a factory with the aid of the National Innovation Foundation is a one-time project, so it calls for a single-use plan.
C. Making the MittiCool house is a standing plan, as it is part of the company’s future plans.
D. Distributing the leftover stock to the quake-affected masses of Kutch is an example of a rule.
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → A and B only
(A) The policy of keeping all products at a lower rate is a standing plan. — True. The price policy is applied every time a product is priced, and policies are standing plans for activities that occur regularly, so A is true.
(B) Starting a factory with the aid of the National Innovation Foundation is a one-time project, so it calls for a single-use plan. — True. The factory is a project that will not be repeated, and a single-use plan is developed for a one-time event or project, so B is true.
(C) Making the MittiCool house is a standing plan, as it is part of the company’s future plans. — False. The MittiCool house is also a one-time project, not likely to be repeated, so it needs a single-use plan; being a future plan does not make it standing.
(D) Distributing the leftover stock to the quake-affected masses of Kutch is an example of a rule. — False. The leftover stock was given away once, after the earthquake, while a rule is a standing plan for activities that occur regularly, so this act is not a rule.
NCERT Extract (2026-27 Edition): Correct statements (A) and (B) Standing Plan: “Standing Plan: A standing plan is used for activities that occur regularly over a period of time. … Standing plans include policies, procedures, methods and rules.” Single-use Plan: “Single-use Plan: A single-use plan is developed for a one-time event or project. …” Incorrect statements (C) and (D) Single-use Plan: “Single-use Plan: A single-use plan is developed for a one-time event or project. Such a course of action is not likely to be repeated in future, i.e., they are for non-recurring situations. …” Standing Plan: “Standing Plan: A standing plan is used for activities that occur regularly over a period of time. … Standing plans include policies, procedures, methods and rules.” |