A can do a piece of work in 30 days and B in 12 days. They work together for 5 days and then both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will C finish the full work? |
32 days 25 days 27 days 24 days |
24 days |
A : B Days 30 : 12 = 2 : 5 Efficiency 5 : 2 Say, the total work = 60 Work done A + B in 8 days = Efficiency x No. Of Days = (2 + 5) x 5 = 7 x 5 = 35 Remaining work = 60 - 35 = 25 This work is completed by C in 10 days, Thus efficiency of C = \(\frac{Work}{Days}\) = \(\frac{25}{10}\) = 2.5 Time taken By C alone to complete this work = \(\frac{Total\; work}{Efficiency}\) = \(\frac{60}{2.5}\) = 24 days |