P can do as much work in 6 days as Q can do in 7, and Q can do as much work in 8 days as R in 5 days. In what time will R do a piece of work which P can do in 8 days ? |
30 days 5\(\frac{5}{6}\) days 5\(\frac{5}{9}\) days 6\(\frac{5}{7}\) days |
5\(\frac{5}{6}\) days |
According To Question , P × 6 = Q × 7 & Q ×8 = R × 5 ( Total work = Efficiency × Number of days ) Ratio of efficiency P : Q & Q : R 7 : 6 5 : 8
So P : Q : R 7× 5 : 6 × 5 5 × 6 : 8 × 6 Combined ratio 35 : 30 : 48 Total work = Efficiency × Number of days let R completed same work in d days as done by P in 8 days P × 8 days work = R × d days work 35 × 8 = 48 × d d = \(\frac{35}{6}\) = 5\(\frac{5}{6}\) days |