If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days? |
70 50 40 80 |
50 |
Formula to be used: ⇒ \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2} \) where, M = no. of men, D = No. of days. Putting values in formula; ⇒ 25 x 140 = \( { M}_{2 } \) x 70 ⇒ \( { M}_{2 } \) = 50 Therefore, 50 men are required to complete the work in 70 days.
|