For designing a tractor, the assembly line production would entail deciding the sequence of various operations, place for men, machines and raw materials etc. All these are part of:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → Method study
Option (1) Motion study — Incorrect. Motion study looks at a worker’s body movements, such as lifting or sitting. It removes the movements that are not needed.
Option (2) Work measurement — Incorrect. This is not one of Taylor’s work-study techniques.
Option (3) Method study — Correct. Method study finds the one best way of doing a job. The standard example is designing a car. Deciding the order of operations and the place for men, machines and raw materials on the assembly line is part of method study. The question uses a tractor in place of a car.
Option (4) Time study — Incorrect. Time study fixes the standard time for a task. It does not plan the layout of an assembly line.
NCERT (2026-27 Edition): “Method Study The objective of method study is to find out one best way of doing the job. There are various methods of doing the job. To determine the best way there are several parameters. …” “For designing a car, the assembly line production would entail deciding the sequence of operations, place for men, machines and raw materials etc. All this is part of method study.” |