A and B, working separately can do a piece of work in 12 days and 20 days respectively. If they work alternately, beginning with A, then in how many days, can the work be completed? |
15 15/2 14/2 14 |
15 |
The correct answer is Option (1) → 15 A’s one-day work = $\frac{1}{12}$ Work done in 2 days (A + B): $\frac{1}{12}+\frac{1}{20}=\frac{5+3}{60}=\frac{8}{60}=\frac{2}{15}$ Work done in 14 days (7 such cycles): $7 \times \frac{2}{15}=\frac{14}{15}$ Remaining work after 14 days: $1-\frac{14}{15}=\frac{1}{15}$ On the 15th day, A works alone. Time taken by A to complete $\frac{1}{15}$ work: $\frac{1/15}{1/12}=\frac{12}{15}=\frac{4}{5}\text{ day}$ So the work is completed during the 15th day. |