If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day? |
36 40 30 24 |
24 |
Formula to be used here, \(\frac{M_1\;×\;D_1\;×\;H_1}{M_2\;×\;D_2\;×\;H_2}\) = \(\frac{W_1}{W_2}\) where, M = No. of men, D = no. of Days, H =No. of hours, W = Unit of work ⇒ Putting values into the formula ⇒ \(\frac{45\;×\;18\;×\;8}{M_2\;×\;20\;×\;9}\) = \(\frac{1}{2/3}\) ⇒ \( { M}_{2 } \) = 24. |