A & B together can complete a work in 30 days. They started work together but after 23 days B left the work and whole work was completed in 33 days. Find the time in which B alone can complete the work. |
100 days 110 days 75 days 150 days |
100 days |
A and B does the work in 30 days, it means A also works for 30 days and B also works for the same 30 days. If B does not work for last 7 days, then that piece of work will be completed by A in 3 days. (after working 30 days) Therefore, B’s 7 days work = A's 3 days work A : B Efficiency : 7 : 3 \(\longrightarrow \) 10 Total work = Time × Total efficiency = 30 × 10 = 300 B (alone) can finish the work in = \(\frac{300}{3}\) = 100 days |