Question:

Which among the following factors affects capital Budgeting decision.

A. Floatation cost
B. Cash flow of project
C. Control considerations
D. The rate of return
E. The investment criteria involved

Choose the correct answer from the options given below.

Options:

B, D and E only

C, A and B only

D, B and C only

A, B and C only

Correct Answer:

B, D and E only

Explanation:

The correct answer is Option (1) - B, D and E only.

A number of projects are often available to a business to invest in. But each project has to be evaluated carefully and, depending upon the returns, a particular project is either selected or rejected. If there is only one project, its viability in terms of the rate of return, viz., investment and its comparability with the industry’s average is seen. There are certain factors which affect capital budgeting decisions.

(a) Cash flows of the project: When a company takes an investment decision involving huge amount it expects to generate some cash flows over a period. These cash flows are in the form of a series of cash receipts and payments over the life of an investment. The amount of these cash flows should be carefully analysed before considering a capital budgeting decision.

(b) The rate of return: The most important criterion is the rate of return of the project. These calculations are based on the expected returns from each proposal and the assessment of the risk involved. Suppose, there are two projects, A and B (with the same risk involved), with a rate of return of 10 per cent and 12 per cent, respectively, then under normal circumstance, project B should be selected.

(c) The investment criteria involved: The decision to invest in a particular project involves a number of calculations regarding the amount of investment, interest rate, cash flows and rate of return. There are different techniques to evaluate investment proposals which are known as capital budgeting techniques. These techniques are applied to each proposal before selecting a particular project.