A can plough a field in 12 hrs and B can do it in 4 hrs. Together with C, they completed the work in 2 hrs. Then, how long does C alone take to do the job? |
6 hrs 3 hrs 7 hrs 12 hrs |
6 hrs |
Let total work = 12, Efficiency of A + B + C = \(\frac{Total\; work}{No.\; of \;hrs}\) =- \(\frac{12}{2}\) = 6 Efficiency of C = eff(A + B + C) - eff(A) - eff(B) = 6 - 3 - 1 = 2 Time taken by C alone = \(\frac{Total\; work}{Efficiency}\) = \(\frac{12}{2}\) =6 hrs
|