Practicing Success
A can finish a piece of work in a certain number of days. B takes 45% more number of days to finish the same work alone. They worked together for 58 days and then the remaining work was done by B alone in 29 days. In how many days could A have completed the work, had he worked alone? |
110 118 98 120 |
118 |
Let number of days taken by A to complete the work = 100 days Number of days taken by B to complete the work = 100 × \(\frac{145}{100}\) = 145 days ratio of A : B Time 100 : 145 20 : 29 Efficiency 29 : 20 ( time and efficiency are inverse to each other ) Let efficiency of A = 29 unit/day Let efficiency of B = 20 unit/day Total work = Efficiency × Number of days Work done by A and B in 58 days = ( 29 + 20 ) × 58 = 2842 unit Remaining work which is done by B in 29 days = 29 × 20 = 580 unit Total work = 2842 + 580 = 3422 unit Time taken by A to complete the whole work = \(\frac{3422}{29}\) = 118 days |