A is 3 times as productive as B. Together they can complete a job in 16.5 days. If C joins them after they have worked for 11 days then in how many days can they finish the rest of the job if C alone can do the job in 12 days. |
2 days \(2\frac{6 }{19}\) days 3 days \(3\frac{3 }{19}\) days |
\(2\frac{6 }{19}\) days |
Let the work done by B = x units/day Therefore work done by A will = 3x units/day Total work = Efficiency × Number of days Total work per = ( 3x + x ) = 4x units Number of days = 16.5 days Total work = 4x × 16.5 = 66x units Work done by A and B together in 11 days = 4x × 11 = 44x units Remaining work = ( 66x - 44x ) = 22x C completed whole work in 12 days , efficiency of C = \(\frac{66x}{12}\) = 5.5x unit/day After 11 days C also joins A and B , so total efficiency = 4x + 5.5x = 9.5x Time taken to complete the remaining work = \(\frac{22x}{9.5x}\) = \(\frac{44}{19}\) = \(2\frac{6 }{19}\) days
|