3 men and 5 women together can complete a work in 6 days, whereas 4 men and 9 women together can do it in 4 days. How many women are required to do the same work in 7 days? |
15 12 14 10 |
12 |
3M + 5W = 6 days, 18M + 30W ..(1) (Multiplied by 6 to get it done in 1 day) 4M + 9W = 4 days, 16M + 36W ..(2) (Multiplied by 4 to get it done in 1 day) Now, (1) - (2), we get ⇒ 2M = 6W ⇒ M : W = 6 : 2 = 3 : 1 (Efficiencies) Putting efficiency in equation (1), and we get the total work, ⇒ [18 (3) + 30(1)] = 84 units. Hence number of Woem needed to complete the work in 7 days = \(\frac{84}{W(1)}\) = 7 days, ⇒ W = 12 |