Target Exam

CUET

Subject

Business Studies

Chapter

Controlling

Question:

Which of the following is NOT a feature of Critical Point Control and Management by Exception?

Options:

They identify critical points

They focus on key result areas

They focus managerial attention on significant deviations

It takes a lot of effort and time as managers have to deal with all deviations

Correct Answer:

It takes a lot of effort and time as managers have to deal with all deviations

Explanation:

The correct answer is option 4- It takes a lot of effort and time as managers have to deal with all deviations.

It takes a lot of effort and time as managers have to deal with all deviations is not a feature of Critical Point Control and Management by Exception.

Some deviation in performance can be expected in all activities. It is, therefore, important to determine the acceptable range of deviations. Also, deviations in key areas of business need to be attended more urgently as compared to deviations in certain insignificant areas. Critical point control and management by exception should be used by a manager in this regard.

Critical Point Control: It is neither economical nor easy to keep a check on each and every activity in an organisation. Control should, therefore, focus on key result areas (KRAs) which are critical to the success of an organisation. These KRAs are set as the critical points. If anything goes wrong at the critical points, the entire organisation suffers. For instance, in a manufacturing organisation, an increase of 5 per cent in the labour cost may be more troublesome than a 15 per cent increase in postal charges.

Management by Exception: Management by exception, which is often referred to as control by exception, is an important principle of management control based on the belief that an attempt to control everything results in controlling nothing. Thus, only  significant deviations which go beyond the permissible limit should be brought to the notice of management. Thus, if the plans lay down 2 per cent increase in labour cost as an acceptable range of deviation in a manufacturing organisation, only increase in labour cost beyond 2 per cent should be brought to the notice of the management. However, in case of major deviation from the standard (say, 5 per cent), the matter has to receive immediate action of management on a priority basis.