P, Q and R can do a piece of work in 45, 30 and 22.5 days respectively. P is assisted by Q on one day and R on the next day alternatively. How long would the work take to finish? |
16\(\frac{3}{5}\) days 16\(\frac{2}{5}\) days 16\(\frac{4}{11}\) days 16\(\frac{3}{7}\) days |
16\(\frac{2}{5}\) days |
1st day work by (P + Q) = 2 + 3 = 5 2nd day work by (P + R) = 2 + 4 = 6 2 days work = 11 16 days work = 88 Remaining work = 90 - 88 = 2 So, remaining work will be done by (P + Q) in = \(\frac{2}{5}\) days. Therefore, the work will be finished in = 16\(\frac{2}{5}\) days |